Planning Application: 19601384 (Tipperary County Council )
File Number:
19601384
Application Type:
PERMISSION
Planning Status:
INCOMPLETED APPLICATION
Received Date:
11/12/2019
Decision Due Date:
Validated Date:
Invalidated Date:
13/12/2019
Further Info Requested:
Further Info Received:
Withdrawn Date:
Extend Date:
Decision Type:
Decision Date:
Leave to Appeal:
Appeal Date:
Commenced Date:
Submissions By:
23/01/2020
Applicant Details
Applicant name:
Ensource Ireland Ltd
Applicant Address:
Phone Number:
Fax Number:
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
The construction of a 43MW Solar PV development comprising of ca. 155,000 no. photovoltaic panels laid out in arrays, the construction of a 38 kV substation, (ca. 114.9m2 X 4.75m tall) and transformer unit (ca. 15.25m2 X 2.4m tall) along with associated ancillary development including: 24 no. Power Hubs (ca. 15.25m” X 2.4m), which incorporate the inverters and the transformers within the same unit, 1 no. single storey communications building (11.1m” X 2.5m), 1 no. single storey client building (15.25m2 X 2.9m), 1 no. single storey equipment storage container (7.5m” X 2.7m), 15 no. CCTV cameras mounted on 4m high poles; and perimeter security fencing. The proposed development will also see the installation of ten (10 no.) ISO shipping container units for the purpose of battery storage (30.5 m” X 2.9m). The total development area will be ca. 70.5 ha
Development Address:
Kyleagarry, Kyle, Ballyryan East and Gortdrum, Co. Tipperary
Kyleagarry, Kyle, Ballyryan East and Gortdrum Donohill Co. Tipperary
the construction of a 43MW Solar PV development comprising of ca. 155,000 no. photovoltaic panels laid out in arrays, the construction of a 38 kV substation, (ca. 114.9m2 X 4.75m tall) and transformer unit (ca. 15.25m2 X 2.4m tall) along with associated ancillary development including: 24 no. Power Hubs (ca. 15.25m” X 2.4m), which incorporate the inverters and the transformers within the same unit, 1 no. single storey communications building (11.1m” X 2.5m), 1 no. single storey client building (15.25m2 X 2.9m), 1 no. single storey equipment storage container (7.5m” X 2.7m), 15 no. CCTV cameras mounted on 4m high poles; and perimeter security fencing. The proposed development will also see the installation of ten (10 no.) ISO shipping container units for the purpose of battery storage (30.5 m” X 2.9m). The total development area will be ca. 70.5 ha
No Environment Impact Assesments Associated with this Application