Planning Application: 19601430 (Tipperary County Council )
File Number:
19601430
Application Type:
PERMISSION
Planning Status:
APPLICATION FINALISED
Received Date:
19/12/2019
Decision Due Date:
29/06/2020
Validated Date:
19/12/2019
Invalidated Date:
Further Info Requested:
20/02/2020
Further Info Received:
02/06/2020
Withdrawn Date:
Extend Date:
Decision Type:
Refused
Decision Date:
29/06/2020
Leave to Appeal:
Appeal Date:
27/07/2020
Commenced Date:
Submissions By:
Applicant Details
Applicant name:
Ensource Ireland Ltd
Applicant Address:
Phone Number:
Fax Number:
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
the construction of a 43MW Solar PV development comprising of ca. 155,000 no. photovoltaic panels laid out in arrays, the construction of a 38 kV substation, (ca. 114.9m2 X 4.75m tall) and transformer unit (ca. 15.25m2 X 2.4m tall) along with associated ancillary development including: 24 no. Power Hubs (ca. 15.25m” X 2.4m), which incorporate the inverters and the transformers within the same unit, 1 no. single storey communications building (11.1m” X 2.5m), 1 no. single storey client building (15.25m2 X 2.9m), 1 no. single storey equipment storage container (7.5m” X 2.7m), 15 no. CCTV cameras mounted on 4m high poles; and perimeter security fencing. The proposed development will also see the installation of ten (10 no.) ISO shipping container units for the purpose of battery storage (30.5 m” X 2.9m). The total development area will be ca. 70.5 ha
Development Address:
Kyleagarry, Kyle, Ballyryan East and Gortdrum, Donohill, Co. Tipperary
Architect Name:
Location Key:
KYLEAGARRY
Electoral Division:
Planner:
Carol Fox
Social Housing Exempt:
Plan Enforcement #:
IPC
Licence Required:
No
Waste Licence Required:
No
Protected Structure:
No
Protected Structure #:
Development Name:
Proposed Development
Comments
Significant Case Flag:
Comments:
Decision
Decision Date:
29/06/2020
Manager Order:
Decision Type:
Refused
Number of Conditions:
2
Grant Date:
Grant Managers Order #:
Section 47
Apply?:
Part 5
Apply?:
Expiry Date:
Decision Description:
the construction of a 43MW Solar PV development comprising of ca. 155,000 no. photovoltaic panels laid out in arrays, the construction of a 38 kV substation, (ca. 114.9m2 X 4.75m tall) and transformer unit (ca. 15.25m2 X 2.4m tall) along with associated ancillary development including: 24 no. Power Hubs (ca. 15.25m” X 2.4m), which incorporate the inverters and the transformers within the same unit, 1 no. single storey communications building (11.1m” X 2.5m), 1 no. single storey client building (15.25m2 X 2.9m), 1 no. single storey equipment storage container (7.5m” X 2.7m), 15 no. CCTV cameras mounted on 4m high poles; and perimeter security fencing. The proposed development will also see the installation of ten (10 no.) ISO shipping container units for the purpose of battery storage (30.5 m” X 2.9m). The total development area will be ca. 70.5 ha
Kyleagarry, Kyle, Ballyryan East and Gortdrum Co. Tipperary
The construction of a 43MW Solar PV development comprising of ca. 155,000 no. photovoltaic panels laid out in arrays, the construction of a 38 kV substation, (ca. 114.9m2 X 4.75m tall) and transformer unit (ca. 15.25m2 X 2.4m tall) along with associated ancillary development including: 24 no. Power Hubs (ca. 15.25m” X 2.4m), which incorporate the inverters and the transformers within the same unit, 1 no. single storey communications building (11.1m” X 2.5m), 1 no. single storey client building (15.25m2 X 2.9m), 1 no. single storey equipment storage container (7.5m” X 2.7m), 15 no. CCTV cameras mounted on 4m high poles; and perimeter security fencing. The proposed development will also see the installation of ten (10 no.) ISO shipping container units for the purpose of battery storage (30.5 m” X 2.9m). The total development area will be ca. 70.5 ha
The development will consist of the construction of Solar PV development comprising photovoltaic panels laid out in arrays over a total development site area of ca. 54.5 ha, the construction of a 38KV substation (ca. 114.4m2 x 4.75m tall), a transformer unit (ca. 18m2 x 4m tall) and associated bund (ca. 55m2) along with ancillary development including: 17 no. Power Hubs (ca. 15.25m2 x 2.4) which incorporate at inverter and a transformer, 1. No. single storey communications building (11.1m2 x 2.5m), 1 no. single storey client side sub-station building (15.25m2 x 2.9) 1. No. single storey equipment storage building (7.5m2 x 2.7m), 7 no. CCTV cameras mounted on 4m high poles, perimeter security fencing and all ancillary works. NIS will be submitted with the planning application
construction of an extension to the solar PV development permitted under planning application ref: PR 22/165 comprising the erection of photovoltaic panels laid out in arrays over a development area of ca. 17.44ha along with ancillary development including: 13 no. inverters (ca. 15.25m2 x 2.6m), 7 no. CCTV cameras mounted on 4m high poles, electrical and communications cabling, palisade security fencing and all ancillary works, this proposed extension development will be connected to an existing permitted solar development under planning application ref: PL 22/165 by underground cables - A Natura Impact Statement will accompany the planning application