ERECTION OF 3 WIND TURBINES WITH A 40 METER HUB HEIGHT AND 52 METER ROTOR DIAMETER, ACCESS TRACKWAYS 4.5METERS IN WIDTH, A20KV SUBSTATION BUILDING, A METEOROLOGICAL MEASURING MAST 40 METERS IN HEIGHT AND ASSOCIATED SITE DEVELOPMENT WORKS
FOR A PERIOD OF TEN YEARS FOR THE ADDITION OF TWO WIND TURBINES TO THE EXISTING THREE TURBINE WINDFARM. THE DEVELOPMENT WILL CONSIST OF THE FOLLOWING: CONSTRUCTION OF (1) TWO WIND TURBINES WITH HUB HEIGHTS OF UP TO 55 METRES AND AN OVERALL HEIGHT OF UP TO 77 METRES TO BLADE TIP; (2) TWO CRANE HARDSTAND AREAS LOCATED BESIDE EACH TURBINE; (3) ONE 20 KV SUBSTATION BUILDING WITH ASSOCIATED ELECTRICAL PLANT AND EQUIPMENT (4) INTERNAL WINDFARM UNDERGROUND CABLING AND NEW SITE ACCESS TRACK AND INSTALLATION OF (1) A DRAINAGE SYSTEM FOR THE PROPOSED HARDSTANDS AND ROAD ACCESS (2) UNDERGROUND GRID CONNECTION OF APPROXIMATELY 910M IN LENGTH, PREDOMINANTELY ALONG THE EXISTING WINDFARM ACCESS ROAD NETWORK AND ALL ASSOCIATED SITE DEVELOPMENT AND ANCILLARY WORKS
No Environment Impact Assesments Associated with this Application