File Number: | 20438 | ||
Application Type: | PERMISSION | Planning Status: | APPLICATION FINALISED |
Received Date: | 15/05/2020 | Decision Due Date: | 28/10/2020 |
Validated Date: | 15/05/2020 | Invalidated Date: | |
Further Info Requested: | 15/07/2020 | Further Info Received: | 21/08/2020 |
Withdrawn Date: | Extend Date: | ||
Decision Type: | Refused | Decision Date: | 28/10/2020 |
Leave to Appeal: | Appeal Date: | 11/11/2020 | |
Commenced Date: | Submissions By: | 07/10/2020 |
Applicant Details |
|||
---|---|---|---|
Applicant name: | THE BALLYLONGFORD WINDFARM GROUP | ||
Applicant Address: | |||
Phone Number: | Fax Number: | ||
Corresp. Address: |
Proposed Development |
|||
---|---|---|---|
Development Description: | AMEND A PREVIOUSLY GRANTED PERMISSION (KERRY COUNTY COUNCIL PLANNING REF 19/381) ( AN BORD PLEANALA REF ABP- 304807-19) WHICH RELATES TO A CHANGE IN THE GRID CONNECTION ROUTE FOR THE PERMITTED WIND FARM. THE REVISED ROUTE WILL ENTAIL THE CONSTRUCTION OF APPROXIMATELY 12.1KM OF 38KV UNDERGROUND ELECTRIC CABLE CONNECTING THE EXISTING PERMITTED WINDFARM (19/381) TO THE 38Kva/110Kva SUBSTATION AT KILPADDOGE, TARBERT. THE UNDERGROUND CABLES WILL BE LOCATED ALONG THE PUBLIC ROADS R551, R552 AND L-1010 AND ALONG 2 SECTIONS OF PRIVATE PROPERTY. THE CABLE WILL BE INSTALLED IN EXCAVATED TRENCHES APPROXIMATELY 1.2M IN DEPTH AND WILL INCLUDE ASSOCIATED UNDERGROUND DUCTING JOINT BAYS, COMMUNICATION CHAMBER BAYS, DRILL PITS, SHEATH LINK BOXES AND INSPECTION CHAMBERS, ASSOCIATED EQUIPMENT AND ALL ANCILLARY SITE AND GROUND WORKS. THE DEVELOPMENT WILL ALSO CONSIST OF THE CONNECTION OF THE PERMITTED WINDFARM (19/381), VIA EXISTING PERMITTED UNDERGROUND ELECTRICITY CABLES, TO THE PROPOSED CABLE.THE UNDERGROUND CABLE WILL BE LOCATED IN THE TOWNLANDS OF BALLYLINE WEST, BALLYMACASY, LISLAUGHTIN, GLANCULLARE SOUTH, GURTEENAVALLIG,MEELCON CARHOONA, FARRANAWANA, DOONARD UPPER, DOONARD LOWER TARBERT AND KILPADDOGE ' THE APPLICANT IS SEEKING A TEN YEAR PLANNING PERMISSION AND OPERATIONAL PERIOD OF 25 YEARS. AN APPROPRIATE ASSESSMENT SCREENING REPORT AND AN ENVIRONMENTAL IMPACT ASSESSMENT SCREENING REPORT HAS BE PREPARED AND SUBMITTED AS PART OF THIS APPLICATION. AN NIS HAS BEEN SUBMITTED WITH THIS APPLICATION | ||
Development Address: | MEELCON, CARHOONA, FARRANAWANA, TARBERT,DOONARD UPPER AND LOWER, KILPADDOGE, BALLYLINE WEST, BALLYMACASY, LISLAUGHTIN, GLAMCULLARE SOUTH, GURTEENAVALLIG, CO KERRY | ||
Architect Name: | R | Location Key: | MEELCON, DOONARD |
Electoral Division: | Planner: | Louise Sexton | |
Social Housing Exempt: | Plan Enforcement #: | ||
IPC Licence Required: | No | Waste Licence Required: | No |
Protected Structure: | No | Protected Structure #: | |
Development Name: |
Comments |
|||
---|---|---|---|
Significant Case Flag: | Comments: | MAIN FILE COLOUR YELLOW WITH 1 X A4 BLUE BF AND 1 X A3 GREEN BF, EIS SUBMITTED WITH THIS APPLICATION |
Decision |
|||
---|---|---|---|
Decision Date: | 28/10/2020 | Manager Order: | |
Decision Type: | Refused | Number of Conditions: | 1 |
Grant Date: | Grant Managers Order #: | ||
Section 47 Apply?: | Part 5 Apply?: | ||
Expiry Date: | 20/06/2026 | ||
Decision Description: | AMEND A PREVIOUSLY GRANTED PERMISSION (KERRY COUNTY COUNCIL PLANNING REF 19/381) ( AN BORD PLEANALA REF ABP- 304807-19) WHICH RELATES TO A CHANGE IN THE GRID CONNECTION ROUTE FOR THE PERMITTED WIND FARM. THE REVISED ROUTE WILL ENTAIL THE CONSTRUCTION OF APPROXIMATELY 12.1KM OF 38KV UNDERGROUND ELECTRIC CABLE CONNECTING THE EXISTING PERMITTED WINDFARM (19/381) TO THE 38Kva/110Kva SUBSTATION AT KILPADDOGE, TARBERT. THE UNDERGROUND CABLES WILL BE LOCATED ALONG THE PUBLIC ROADS R551, R552 AND L-1010 AND ALONG 2 SECTIONS OF PRIVATE PROPERTY. THE CABLE WILL BE INSTALLED IN EXCAVATED TRENCHES APPROXIMATELY 1.2M IN DEPTH AND WILL INCLUDE ASSOCIATED UNDERGROUND DUCTING JOINT BAYS, COMMUNICATION CHAMBER BAYS, DRILL PITS, SHEATH LINK BOXES AND INSPECTION CHAMBERS, ASSOCIATED EQUIPMENT AND ALL ANCILLARY SITE AND GROUND WORKS. THE DEVELOPMENT WILL ALSO CONSIST OF THE CONNECTION OF THE PERMITTED WINDFARM (19/381), VIA EXISTING PERMITTED UNDERGROUND ELECTRICITY CABLES, TO THE PROPOSED CABLE.THE UNDERGROUND CABLE WILL BE LOCATED IN THE TOWNLANDS OF BALLYLINE WEST, BALLYMACASY, LISLAUGHTIN, GLANCULLARE SOUTH, GURTEENAVALLIG,MEELCON CARHOONA, FARRANAWANA, DOONARD UPPER, DOONARD LOWER TARBERT AND KILPADDOGE ' THE APPLICANT IS SEEKING A TEN YEAR PLANNING PERMISSION AND OPERATIONAL PERIOD OF 25 YEARS. AN APPROPRIATE ASSESSMENT SCREENING REPORT AND AN ENVIRONMENTAL IMPACT ASSESSMENT SCREENING REPORT HAS BE PREPARED AND SUBMITTED AS PART OF THIS APPLICATION. AN NIS HAS BEEN SUBMITTED WITH THIS APPLICATION |
Appeal Details | |||
---|---|---|---|
Notification Date: | 13/11/2020 | BP Reference #: | 308643-20 |
Appeal Type: | APPLICANT | File Forward Date: | 24/11/2020 |
Submission Due Date: | 10/12/2020 | Submission Sent Date: | 01/12/2020 |
Appeal Decision: | CONDITIONAL | Decision Date: | 21/06/2021 |
Withdrawn Date: | Dismissed Date: | ||
Reason: |