23404 |
APPLICATION FINALISED |
PERMISSION |
C |
14/04/2023 Friday |
Cagney Maintanance Services Ltd |
Unit 16, The Hub Logistics Park Bracetown Co. Meath, D15 V997 |
the development will consists of (a) the proposed change of use of 305m2 of the existing product display area and spares storage area on the ground floor to proposed office use including associated canteen; (b) the change of use of 242m2 of the existing ancillary storage area on the first floor to proposed office, training, innovation and product display areas, and (c) new external 1m high x 4.4m wide signage on the Northwest & Southeast Elevations |
DA50233 |
APPLICATION FINALISED |
PERMISSION |
C |
24/06/2005 Friday |
Hickwell Ltd. |
Gunnocks & Bracetown Clonee Co. Meath |
the construction of a logistics, warehousing and light industrial development comprising of 6 no.units of 508sq.m, 1,102sq.m., 1,469sq.m., 2,094 sq.m., 5,950sq.m., 7,665 sq.m.(total gross floor area of 18,788 sq.m.). The development also includes a new vehicular access from the Kilbride Road (CR580), internal roads, attenuation pond, car parking, heavy goods vehicle parking, loading and docking bays, separate service delivery and vehicular access, 2 no. ESB substations, 1 no. ancillary waste recycling compound, connection to existing treatment plant at Bracetown Business Park and all associated site development and landscaping works on a site of 7ha. |
DA101063 |
APPLICATION FINALISED |
EXTENTION OF DURATION |
C |
17/09/2010 Friday |
Hickwell Ltd |
Gunnocks & Bracetown Clonee Co Meath |
DA50233 - Construction of a logistics, warehousing and light industrial development comprising of 6 no. units of 508sq.m., 1,102sq.m., 2,094sq.m., 7,665sq.m.(total gross floor area of 18,788sq.m.). The development also includes a new vehicular access from the kilbride Road (CR580), internal roads, attenuation ponds, car parking, heavy goods vehicle parking, loading and docking bays, separate service delivery and vehicular access, 2 no. ESB Substations, 1 no ancillary waste recycling compound, connection to existing treatment plant at Bracetown Business Park and all associated site development and landscaping works on a site of 7ha at Gunnocks & Bracetown, Clonee, Co.Meath |
RA150972 |
APPLICATION FINALISED |
PERMISSION |
C |
16/09/2015 Wednesday |
Hickwell Ltd. |
The Hub Logistics Park, Bracetown (and including lands within the townlands of Bracetown; Gunnocks & Portmanna) Clonee, Co. Meath |
development at a site at The Hub Logistics Park, Bracetown (and including lands within the townlands of Bracetown, Gunnocks & Portmanna), Clonee, County Meath. A 10 year permission is being sought. The development will consist of an extension to the existing logistics park, permitted under Reg. Ref. DA50233, comprising of 3 no. additional logistics, warehousing and light industrial units of 6,480sqm; 9,792sqm and 12,672sqm gross floor area, respectively (total gross floor area of 28,944sqm), all with a maximum building height of approximately 15.75m. Access to the proposed development will be via the existing entrance and internal access route to The Hub Logistics Park. The development provides for the extension of and provision of new internal roads; a total of 266 no. surface car parking spaces; and all associated heavy goods, vehicle parking, loading and docking bays. The development also includes associated and ancillary site development works including attenuation pond to serve the proposed units, site services; landscaping, boundary treatments; lighting; and all associated site development and works |
RA151340 |
APPLICATION FINALISED |
RETENTION PERMISSION |
C |
10/12/2015 Thursday |
Beko Ireland |
Unit 16, (granted as Unit E01) The Hub Logistics Park Gunnockstown & Bracetown, Clonee, Co. Meath |
retention permission for the following amendments to Unit E01 previously approved planning Reg. Ref. No. DA/50233 at Gunnocks & Bracetown, Clonee, Co. Meath. (1) Retention of revised site layout. (2) Retain revised elevation treatment to unit E01. (3) Retention of first floor offices and ancillary storage area |