the development will consist of amendments to An Bord Pleanala permission reference 312771-22 to consist of the following:
1. Removal of condition 3 which states ‘The buildings hereby permitted, and all activities occurring therein, shall only operate between 0700 hours and 2100 hours, Monday to Friday and between 0700 and 1430 hours on Saturdays. No activity shall take place outside these hours or on Sundays or public holidays.’
2. Amendments to the site boundary.
3. Amendments to the design and layout of units 10, 12 and 13.
4. Provision of an acoustic berm and associated landscaping works.
5. Amendments to the site layout.
6. Omission of the temporary wastewater treatment plant with connections made to the public mains for wastewater services.
7. Associated site works to include for revised parking, loading and turning areas along with drainage, landscaping, external lighting.’
Development Address:
Lands at, City North Business Campus, Stamullen, Co Meath
Architect Name:
Location Key:
STAMULLEN
Electoral Division:
Incorrect Icl Voter Recor
Planner:
Peadar McQuaid
Social Housing Exempt:
Plan Enforcement #:
IPC
Licence Required:
No
Waste Licence Required:
No
Protected Structure:
No
Protected Structure #:
Development Name:
Proposed Development
Comments
Significant Case Flag:
Comments:
Decision
Decision Date:
20/02/2025
Manager Order:
390/25
Decision Type:
Conditional
Number of Conditions:
10
Grant Date:
07/04/2025
Grant Managers Order #:
Section 47
Apply?:
Part 5
Apply?:
Expiry Date:
06/04/2030
Decision Description:
the development will consist of amendments to An Bord Pleanala permission reference 312771-22 to consist of the following:
1. Removal of condition 3 which states ‘The buildings hereby permitted, and all activities occurring therein, shall only operate between 0700 hours and 2100 hours, Monday to Friday and between 0700 and 1430 hours on Saturdays. No activity shall take place outside these hours or on Sundays or public holidays.’
2. Amendments to the site boundary.
3. Amendments to the design and layout of units 10, 12 and 13.
4. Provision of an acoustic berm and associated landscaping works.
5. Amendments to the site layout.
6. Omission of the temporary wastewater treatment plant with connections made to the public mains for wastewater services.
7. Associated site works to include for revised parking, loading and turning areas along with drainage, landscaping, external lighting.’
Lands at City North Business Campus Stamullen Co Meath
1. Permission for a warehouse unit with a cumulative gross floor area of 6806.3sq.m of which the warehouse area comprises 4674.4sq.m at ground floor along with a mezzanine floor area comprising 351.8sq.m, the provision of a ground floor office and staff areas comprising 760.4sq.m along with a first floor office comprising 484.2sq.m and a second floor plant storage area comprising 525.4sq.m. The warehouse building will have an overall height of 14.65 metres.
2. Vehicular access will utilise the existing City North Campus Estate roads.
3. The development of associated internal access roads, turning/loading areas, footways, parking areas, electric vehicle charge points and associated ducting, landscaping, lighting, fencing, bicycle and bin storage facilities and associated site works.
4. The provision of façade signage along with provision of a totem sign.
5.The provision of an ESB substation.
6. Provision of attenuation tanks and associated infrastructure as part of the surface water system along with installation of a bypass hydrocarbon interceptor.
7. All ancillary site development, landscaping and construction works to facilitate foul, water and service network connections.
An Environmental Impact Assessment Report (EIAR) has been prepared in respect of the proposed development and accompanies this application.
the development will consist of construction of 3 no. new warehouse buildings with a cumulative gross floor area (GFA) of 23,380sq.m. The buildings are to be situated in the west of the site and shall comprise the following: i. Unit 10 will have a GFA of 8,013sq.m, including a warehouse area of 7,203sq.m and 2-storey office element of 810sq.m, with a maximum height of 14.520m; ii Unit 12 will have a GFA of 5,786sq.m, including warehouse area of 5,206sq.m and 2-storey office element of 580sq.m, with a maximum height of 14.520m; and iii Unit 13 will have a GFA of 9,581sq.m, including a warehouse area of 8,665sq.m and 2-storey office element of 916sq.m, with a maximum height of 14.520m. Vehicular access to the site will utilize the existing City North Business Campus estate roads and include construction of new internal roads and accessways to serve the proposed development. A total of 302 no. car parking spaces will be provided including 104 no. spaces for Unit 10, 75 no. spaces for Unit 12 and 123 no. spaces for Unit 13, as well as a total of 102 no. secure bicycle parking spaces. A temporary wastewater treatment plant is to be provided adjacent to the south-east site boundary to serve all 3 no. warehouse buildings for the treatment of foul effluent before discharge to the existing network.1 no, ESB substation is proposed (c.21.8sq.m and 2.715m in height) to serve the 3 no. buildings, located adjacent to Unit 10. The proposal also consists of ancillary site works to facilitate the development including drainage, landscaping and external lighting to roads and main circulation routes. Significant further information/revised plans submitted on this application , including an EIA(R)
No Environment Impact Assesments Associated with this Application