Planning Application: 03674 (Monaghan County Council )
File Number:
03674
Application Type:
PERMISSION
Planning Status:
APPLICATION FINALISED
Received Date:
29/08/2003
Decision Due Date:
23/10/2003
Validated Date:
29/08/2003
Invalidated Date:
Further Info Requested:
Further Info Received:
Withdrawn Date:
Extend Date:
Decision Type:
Conditional
Decision Date:
22/10/2003
Leave to Appeal:
Appeal Date:
Commenced Date:
Submissions By:
Applicant Details
Applicant name:
Silver Hill Foods
Applicant Address:
Phone Number:
Fax Number:
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
erect an effluent treatment plant and anaerobic digester plant consisting of a main processing and storage building , a chemical store and polymer makeup building, 500 cubic metre effluent day tank, 100 cubic metre under ground anaerobic digester feed tank and ancillary biogas handling facility , 100 cubic metre underground polymer mixing tank, process cooling tank, 145 cubic metre bunded digester containment tank and permission to erect 1147 cubic metre balance tank and 517 cubic meter anoxic tank and ancillary site works
erect an effluent treatment plant and anaerobic digester plant consisting of a main processing and storage building , a chemical store and polymer makeup building, 500 cubic metre effluent day tank, 100 cubic metre under ground anaerobic digester feed tank and ancillary biogas handling facility , 100 cubic metre underground polymer mixing tank, process cooling tank, 145 cubic metre bunded digester containment tank and permission to erect 1147 cubic metre balance tank and 517 cubic meter anoxic tank and ancillary site works
erect three number duck houses and associated hardstanding yard area, new entrance onto existing company private access road, upgrading of exisiting rising main and connection into existing company foul sewer network and storm water collection network and all associated site development and drainage works
to erect: (1) Three number duck houses and associated hardstanding yard area. (2) New entrance onto existing company private access road. (3) Upgrading of exisiting rising main and connection into existing company foul sewer network and storm waste collection newwork and all associated site development and drainage works
No Environment Impact Assesments Associated with this Application