Planning application details ref: 211620 Tipperary County Council

100%100% Complete (warning)

Planning Application: 211620 (Tipperary County Council )
File Number: 211620
Application Type: PERMISSION Planning Status: APPLICATION FINALISED
Received Date: 05/11/2021 Decision Due Date: 17/10/2022
Validated Date: 05/11/2021 Invalidated Date:
Further Info Requested: 06/01/2022 Further Info Received: 23/08/2022
Withdrawn Date: Extend Date:
Decision Type: Conditional Decision Date: 11/10/2022
Leave to Appeal: Appeal Date:
Commenced Date: Submissions By: 26/09/2022

Applicant Details

Applicant name: Gromane Limited
Applicant Address:
Phone Number: Fax Number:
Corresp. Address:

Applicant Details


Proposed Development

Development Description: a ten-year appropriate period planning permission for development of this site: the proposed development will constitute the provision of the following: the installation of 2.25 km of 38kV underground grid connection comprising cable ducting and associated electrical cabling and all other ancillary works including joint bays, culverts, maker posts and all associated developments. Advisory Note: The full extent of the grid connection is 33.8 km, and a separate planning application will be made for a underground grid connection to Kilkenny County Council. This development comprises part of an overall development for which planning permission was granted for a 9 turbine wind farm and all associated works on lands located in the townlands of Farranrory Upper, Farranrory Lower, Coolnashinnagh and Gortnasmuttaun, Co. Tipperary. The planning application will be accompanied by an Environmental Impact Assessment Report (EIAR) and Natura Impact Statement
Development Address: Coolanshinnagh, Ardragh, Gortfree, Bolakeale, Co. Tipperary
Architect Name: Location Key: COOLNASHINNAGH
Electoral Division: Planner: Jonathan Flood
Social Housing Exempt: Plan Enforcement #:
IPC Licence Required: No Waste Licence Required: No
Protected Structure: No Protected Structure #:
Development Name:

Proposed Development


Comments

Significant Case Flag: Comments:

Decision

Decision Date: 11/10/2022 Manager Order:
Decision Type: Conditional Number of Conditions: 5
Grant Date: 14/11/2022 Grant Managers Order #:
Section 47 Apply?: Part 5 Apply?:
Expiry Date: 13/11/2032
Decision Description: a ten-year appropriate period planning permission for development of this site: the proposed development will constitute the provision of the following: the installation of 2.25 km of 38kV underground grid connection comprising cable ducting and associated electrical cabling and all other ancillary works including joint bays, culverts, maker posts and all associated developments. Advisory Note: The full extent of the grid connection is 33.8 km, and a separate planning application will be made for a underground grid connection to Kilkenny County Council. This development comprises part of an overall development for which planning permission was granted for a 9 turbine wind farm and all associated works on lands located in the townlands of Farranrory Upper, Farranrory Lower, Coolnashinnagh and Gortnasmuttaun, Co. Tipperary. The planning application is accompanied by an Environmental Impact Assessment Report (EIAR) and Natura Impact Statement

Appeal Details


Appeal Details
Notification Date: BP Reference #:
Appeal Type: File Forward Date:
Submission Due Date: Submission Sent Date:
Appeal Decision: Decision Date:
Withdrawn Date: Dismissed Date:
Reason: